The official deadline for the Goa state solar subsidy is 31st March 2026. However, it's crucial to understand that this deadline is not just about paperwork - it's about getting your solar plant fully connected to the grid by that date.
In practical terms, grid connection can take up to two months from the time your installation is completed. This means that to ensure you don't miss out on the subsidy, your solar installation needs to be finished well in advance.
In other words, the real cut-off date to start your solar project is closer to 31st January 2026.
By starting your installation early, you allow enough time for all necessary steps: planning, installation, inspection, and the final grid connection. Waiting until the last minute could mean missing out entirely on the subsidy.
At Anmax Energy, we handle everything from initial quote to final grid connection, and we'll make sure your project is completed on time. But to guarantee your subsidy, we strongly recommend beginning the process as soon as possible.
Don't wait -take action now to secure your subsidy and start saving with solar energy in Goa!